The elevator on Ulrikedalsvägen 8A is from the 1960s and will be replaced with a new modern elevator. The work takes about six weeks and during this time the elevator will be completely shut down.

Timetable

Work on replacing the lift will start on Monday 11 October and is expected to be completed on Tuesday 16 November. The work takes place on weekdays between 08:00-16:00.

Disruptions

While the work is in progress, the elevator is completely closed for use. The stairs can be used as usual.

The work will occasionally be noisy, especially the first two weeks when demolition work is done in the elevator shaft.

Thanks for your patience. We hope that you will enjoy the new elevator!

Contact

If you have any questions, please contact Project Manager Rickard Wallin at rickard.wallin@afbostader.se or +46 (0) 46 19 15 60.

 